Dear Nattering nabobs of negativism,
I just wanted to provide you with an end-of-August update on the large PSE&G Energy Strong Gas Glen Avenue modernization project that has been periodically causing traffic delays in the Village throughout the summer. The good news is that, barring any unforeseen circumstances, the major infrastructure work will be done by this Friday. The other good news is that the planned work has been completed on East Glen so there should be no detour issues impacting Travell School.
Over the next two days, the intersection of Monroe and Glen will be closed while work is being done; this will cause a significant detour and associated traffic problems. Please try to avoid this route as much as possible.
In the next several weeks, through late September, individual service line hook-ups will be scheduled with homeowners along West Glen. These hook-ups could result in intermittent lane closures.
Thanks for your patience during this period – we have been fortunate that, in working closely with PSE&G, they were able to complete the most impactful part of this project within the summer months. We are also fortunate that this major PSE&G project of modernization to our gas lines enhances the safety, cleanliness and reliability of the services that we rely on.
We are almost at the finish line!
Best,
Roberta Sonenfeld
Village Manager
201-670-5500, ext. 203