Ridgewood Water ; Water Main Replacements at Stream Crossings

Ridgewood Water

December 19,2017
the staff of the Ridgewood blog

Ridgewood NJ, The project is progressing along with two of the stream crossings, East Ridgewood Ave. & North Irving St. completed with the exception of final restoration which will be completed in the Spring of 2018. The third stream crossing, Spring Avenue is 60% completed.

Keeping to schedule, Deven’s Construction will mobilizing to the fourth stream crossing, Linwood Avenue during the week of December 4th. Construction activities will include moving equipment and materials on site followed-up by mobilization of the crew. The first order of business will be to install the sheet piling in the stream bed and construction of the new water main thru the stream. We anticipate approximately 5 – 7 weeks for completion of the entire Linwood Avenue water main reconstruction barring any unforeseen conditions and inclement weather.

Devens Construction will be coordinating with the Ridgewood police who will be directing traffic around work areas on an as needed basis. Expected work hours will be Monday through Friday, 7am – 4:30pm, with possible Saturday work.

  • New water main
  • East Ridgewood Ave. & North Irving St
  • Monday through Friday, 7am – 4:30pm