August 29,2017
the staff of the Ridgewood blog
Ridgewood NJ, During milling and paving, access to your driveway will be restricted for the entire day while work is being done in front of your home. It will be best to park on a side street for the entire day. Work will start daily at 7:00 a.m. Schedule is pending weather conditions and unforeseen circumstances.
Jovan Mehandzic, will be the Village’s on-site inspector. If you have any questions, concerns or special needs, please contact Mr. Mehandzic preferably by email at [email protected]. Otherwise you can reach them on their cell phones at 201-523-0158 (Jovan M) .Finally, make a copy of this notice and place it on the dashboard of your vehicle when you park on a side street
2017 Paving Notice
The Village Council has awarded the paving contract to J.A. Alexander., to resurface your
street. The follow is the anticipated schedule.
MILLING SCHEDULE
Monday, August 28
Stevens Avenue
(Grove Street to Corella Ct)
Brookside Avenue
(E. Ridgewood Avenue to Spring Ave)
Tuesday, August 29
Bedford Road
(Morningside Rd to Wellington Rd)
Bogert Avenue
(E.Glen Avenue to Meadowbrook Ave)
Wednesday, August 30
S. Hillside Place
(W. Ridgewood Ave to S. Monroe St)
S. Monroe Street
(W. Ridgewood Ave to Godwin Ave)
PAVING SCHEDULE
Thursday, August 31
S. Hillside Place
(W. Ridgewood Ave to S. Monroe St)
S. Monroe Street
(W. Ridgewood Ave to Godwin Ave)
Friday, September 1
Stevens Avenue
(Grove Street to Corella Ct)
Brookside Avenue
(E. Ridgewood Avenue to Spring Ave)
Tuesday, September 5
Bedford Road
(Morningside Rd to Wellington Rd)
Bogert Avenue
(E.Glen Avenue to Meadowbrook Ave)