Ridgewood NJ, For those of you who believe the Village is consistently able to bring a projects in on time and within budget, I offer this as evidence of my concerns regarding the issue.
A seemingly routine contract award by the Village Council in February jumped 288% within nine (9) months due to two (2) change orders.
And this is the same Village Council that may be awarding a contract for a $15 million parking garage.
Enough said.
**********
February
15-35 Award Contract – Servicing and Repair of Potable Water Pumping Facilities (NTE $66,813.10) – Awards the second year of a two year contract to the lowest responsible bidder, Rinbrand Well Drilling, 14 Waldron Avenue, Glen Rock, NJ
July
15-219 Authorize Change Order – Servicing & Repair of Potable Water Pumping Facilities ($60,000)- Authorizes a change order to the original contractor, Rinbrand Well Drilling Co., Inc., 14 Waldron Avenue, Glen Rock, NJ which is necessary due to additional necessary repairs to pumping facilities
November
15-361 Authorize Change Order – On-Call Servicing and Repair of Potable Well Facilities and Piping (NTE $132,650.42) – Authorizes a change order to the original contractor, Rinbrand Well Drilling Company, Inc., 14 Waldron Avenue, Glen Rock, NJ. This change order is necessary due to additional necessary repairs to pumping facilities.
$ 66,813.10
$ 60,000.00
$132,650.42
_____________
$259,463.20