Twp. of Washington NJ, PASCACK ROAD PAVING INFORMATION – The milling and paving project is set to begin 8/28 and will be the entire length of Pascack Road from Linwood Avenue to Hillsdale Municipal Line/Ell Road. The hours of work will be 7 am to 5 pm.
The start date and the anticipated completion date are subject to change due to unforeseeable weather events.
Concrete Work – 8/28 to 9/8
Milling – 9/11 to 9/15
Paving – 9/18 to 9/20
*Detour information will be posted by the Twp. of Washington Police when available.
*The resurfacing of Washington Avenue was discussed. The county has not received its state funding for Washington Avenue as of yet and anticipate the work to be performed in 2024.