December 2013 PSE&G ELECTRIC RELIABILITY IMPROVEMENTS 69K V UTILITY INFRASTRUCTURE UPGRADE
SCHEDULE DECEMBER 2013–FEBRUARY 2014
VILLAGE OF RIDGEWOOD
As part of our electric reliability improvement s in Bergen County, PSE&G will be performing utility pole line work in the Village of Ridgewood. Starting on or about December 9th
through late February 2014, PSE&G will be performing the following activities in
your area:
Anticipated Schedule Activity Location Anticipated Traffic Impacts
Dec. 9-Dec. 15 Wire Work & Pole Sets S.Maple Avenue (Park Avenue to Spring Avenue) Limited Lane or Road Closure
Dec. 9-Dec. 13 Vegetation Management Spring Avenue Limited Lane or Road Closure
Dec. 16-Dec. 20 Wire Work & Pole Sets Spring Avenue & Hope Street Limited Lane or Road
Closure
Dec. 26- Dec. 29 Vegetation Management Hope Street Limited Lane or Road Closure
Dec. 26-Dec. 29 Pole Sets East Ridgewood Avenue (S. Irving Street to S. Van Dien Avenue)
Full Road Closure
Dec. 30-Feb. 28 Wire Work & Pole Sets East Ridgewood Avenue (S. Irving Street to Paramus
Road) Limited Lane or Road Closure
Excluding inclement weather delays,PSE&G anticipates working Monday–Friday (9am–5pm)
, as well as Saturday and Sunday (8am–5pm) on an as needed basis,in order to complete our work as quickly as possible.
PSE&G will work closely with the Village of Ridgewood Police Department to minimize traffic
impacts. All work will be performed in accordance with all PSE&G safety and environmental standards and no interruption of electric service is anticipated.
Upon project completion, these upgrades will increase both electric service capacity and system redundancy to ensure safe and more reliable electric service to our customers. Questions about this project can be directed to PSE&G’s Electric Utility Upgrade contact number: 1-800-901-5035.
So after all the controversy and emotions, PSE&G has decided to actually do the work the week of Christmas on Hope St. and Ridgeood Ave. Way to keep it classy PSE&G. Nothing quite says the holidays like cutting down trees and transforming a charming street into a right of way for high tension power lines. It just shows how tone deaf and sleazy this company really is.
Where was this schedule posted….. thanks.
Boyd, where did you find this schedule ???
Vegetation management is what you call the butchering of trees with no top or middle. This of course must be a joke.
Since the pole guys are here.. how about replacing the pole on North Monroe @ Valley View that’s about to fall over.
The half-assed repair *tying rope around the base* doesn’t quite cut it.
Dr. Fishbein sent it out to parents.
Also posted on Village website home page.
Reliability improvements. Vegetation management. Wish those marketing people were standing under a 90-foot pole with live wires on it.