Elements of the Village Gas Service Upgrade Project :

• Ferreira Construction will again use Village Police Officers for traffic control, like they did for the work in the East Glen Avenue area earlier this year.

• There will be no steel road plates used. All parties agreed to this.

• Trenches will be topped with hot mix I-5 asphalt mix, followed by final restoration later.

• The contractor’s crews would like to work 6 days per week, weather and Village permitting. No work on Sunday.

• Trenches will be generally 18-inches wide.

• House services will be done after the main work is complete, but coordinated to minimize natural gas service interruptions during the winter heating days.

• Ferreira will continue to use their current staging area. Some equipment will be left on streets overnight in the Lawns area.

• Work will not occurred during inclement weather periods.

Click Here for Map of roads scheduled for work

One thought on “PSE&G – Energy Strong Gas Upgrade Project – Phase II

  1. I hope they are going repave the streets when done. because on vesta they destroyed the road surface. . I had a blow out on my car.

Leave a Reply

Your email address will not be published.