Posted on

RIDGEWOOD PSEG – CONSTRUCTION NOTICE UPDATE JANUARY 30, 2017

PSEG

file photo by Boyd Loving
IMPORTANT UPDATE REGARDING PSE&G Work Schedule January 30 – February 3:
Village of Ridgewood
Updated: January 26, 2017
PSE&G ELECTRIC RELIABILITY IMPROVEMENTS
UTILITY UNDERGROUND INFRASTRUCTURE UPGRADE
WORK SCHEDULE UPDATE: January 30, 2017 – February 3, 2017

January 30, 2017 – February 3, 2017

Underground Manholes & Pipe Installation

South Broad Street

(Hudson Street & E. Ridgewood Avenue)

Road or Lane Closures

(7:00am – 5:00 pm)

Monday- Friday

8 Parking Spots

January 29,2017

the staff of the Ridgewood blog

Ridgewood NJ, As part of our electric reliability improvements in Bergen County, PSE&G will be performing utility underground work in the Village of Ridgewood. As of mid-January 2017, PSE&G will be performing the following activities in your area:

Excluding inclement weather delays, PSE&G anticipates working Monday –Friday, (7:00am – 5:00pm)

Safety is our primary concern. PSE&G will work with the Ridgewood Police Department to minimize any traffic concerns or inconveniences to the public. Please be advised that Ridgewood Police Department may close additional spaces to ensure public safety. In addition, during construction, please refrain from going near our construction work zones.

The upgrades will enhance your electric capacity, system redundancy, and service reliability within the Village of Ridgewood, as well as surrounding communities. If you have questions or concerns, please call our toll free number at 1-877-678-5784