Controversial utility poles to be installed
Saturday, December 7, 2013
BY CHRIS HARRIS
STAFF WRITER
The Record
RIDGEWOOD — Crews from Public Service Electric and Gas will return to Ridgewood next weekend, despite months of objections from village officials and residents.
Work will resume to install new utility poles on Hope Street and Spring Avenue on Dec. 14 and Dec. 15. The work is scheduled to commence at 8 a.m. and continue through 5 p.m. on each day.
More poles will then be installed Dec. 28 and Dec. 29 in front of Ridgewood High School, as part of PSE&G’s efforts to connect substations in Fair Lawn and Paramus.
The work will resume less than a month after the state’s Board of Public Utilities denied a request from the village, seeking the continuation of a moratorium on the pole installations.
The board’s decision cleared the way for the project to continue; work has been on hold since the summer, when residential opposition first began.
Residents of Hope Street and Spring Avenue in July complained to village officials, saying the poles — which, at 65 feet tall, soar above the neighborhood’s treetops — would diminish property values and pose serious health and safety considerations.
Representatives from PSE&G met with the village on Wednesday morning, to offer up a timeline on when the project would continue.
On Monday, poles will be installed on Maple Avenue.
– See more at: https://www.northjersey.com/news/234861621_Controversial_utility_poles_to_be_installed.html#sthash.apos2ZJ5.dpuf