Ridgewood Water Continues to Make Progress With Water Main Upgrade

Ridgewood Water

November 18,2017

the staff of the Ridgewood blog

Ridgewood NJ, Ridgewood Water has offered an update on the Water Main Replacements at Stream Crossings. Ridgewood Water announced  in July it was going to upgrade water mains at four stream crossings. Water mains were to be replaced at four stream crossing :

Linwood Ave. at the Saddle River
North Irving St. at the HoHoKus Brook
East Ridgewood Ave. at the HoHokus Brook
Spring Ave. at the Hohokus Brook

Construction activities have been completed at the East Ridgewood Avenue stream crossing and nearly completed at the North Irving Avenue stream crossing.  Final testing and tie-ins will be completed this week at North Irving Street.

In the meantime, Devens Construction will mobilizing to the third stream crossing, Spring Avenue on or about Tuesday, November 14th.  Construction activities will include setting up temporary fencing for pedestrian traffic and moving equipment and materials on site, followed by sheet piling of the stream bed and construction of the new water main.  We anticipate approximately six (6) weeks for completion of the Spring Avenue stream crossing barring any unforeseen conditions.

Devens Construction will be coordinating with the Ridgewood police who will be directing traffic around work areas on an as-needed basis.   Expected work hours will be Monday through Friday, 7am – 5:30pm, weather permitting and possible Saturday workday.