PSE&G – Energy Strong Gas Upgrade Project – Phase II has begun in the Lawns Area
Elements of the Gas Service Upgrade Project :
• Ferreira Construction will again use Village Police Officers for traffic control, like they did for the work in the East Glen Avenue area earlier this year.
• There will be no steel road plates used. All parties agreed to this.
• Trenches will be topped with hot mix I-5 asphalt mix, followed by final restoration later.
• The contractor’s crews would like to work 6 days per week, weather and Village permitting. No work on Sunday.
• Trenches will be generally 18-inches wide.
• House services will be done after the main work is complete, but coordinated to minimize natural gas service interruptions during the winter heating days.
• Ferreira will continue to use their current staging area. Some equipment will be left on streets overnight in the Lawns area.
• Work will not occur during inclement weather periods.
They started on Newcomb, Amazing progress, that crew works non stop, fascinating and very well coordinated.
I’m sure they move quickly because they are probably paid ‘per foot’ of pipe installed vs ‘per hour’.
Money is a motivator.
I hope they repair the roads . and clean up the mess.