BCIA RIDGEWOOD PARKING FINANCIAL SUMMARY
This document produced by BCIA Professionals contrasts BCIA County Guaranteed Financing with Village of Ridgewood Stand Alone Financing for debt associated with the Parking Deck Project. Please note that the estimated differential between the two scenarios has changed since last week, due to changes in BCIA issuance costs amended by the BCIA on Friday, January 29, 2016. Now, there is an estimated differential of $22,248 which averages less than $900 per year. Click Here for the document.
DESMAN HUDSON STREET DECK DRAWINGS – 1/29/2016
These drawings represent the site plan, floor plan & building sections for the revised design of the Deck at Hudson Street. This Deck design was first considered in October 2015. There will be 325 parking spots. The height to the roof is approx. 43′ and 46′ 8″ to the parapet. Click Here for Drawings