UPDATED SCHEDULE: PSE&G ELECTRIC RELIABILITY IMPROVEMENTS
UTILITY UNDERGROUND INFRASTRUCTURE UPGRADE
WORK SCHEDULE UPDATE: February 6, 2017 – February 10, 2017
February 6, 2017 –February 10, 2017
Underground Manholes & Pipe Installation
South Broad Street
(at the cross section of Ridgewood Avenue)
Road Closures
(7:00am – 5:00 pm)
Monday- Friday
8 Parking Spots
As part of our electric reliability improvements in Bergen County, PSE&G will be performing utility underground work in the Village of Ridgewood. As of early-February 2017, PSE&G will beperforming the following activities in your area:
Excluding inclement weather delays, PSE&G anticipates working Monday –Friday, (7:00am – 5:00pm)
Safety is our primary concern. PSE&G will work with the Ridgewood Police Department to minimize any traffic concerns or inconveniences to the public. During construction, please refrain from going near our construction work zones.
The upgrades will enhance your electric capacity, system redundancy, and service reliability within the Village of Ridgewood, as well as surrounding communities. If you have questions or concerns, please call our toll free number at 1-877-678-5784