Ridgewood Drivers Alert: Major 3-Week Maple Avenue Paving Project Set to Begin

IMG 20260714 114300985 BURST000 COVER scaled

Long-Awaited Maple Avenue Paving Project Set to Begin: Full Ridgewood Schedule & Detour Info

photo Maple Ave warmup

the staff of the Ridgewood blog

RIDGEWOOD, NJ — Local drivers and residents should prepare for upcoming detours as the highly anticipated resurfacing of Maple Avenue officially gets underway.

Managed by Bergen County’s retained paving contractor, Tilcon, the major infrastructure project will refresh Maple Avenue all the way from the Ho-Ho-Kus border to the Glen Rock border.

Staging for construction equipment will begin in the Graydon South Parking Lot. The entire project is expected to take approximately three weeks, weather permitting. Because work will progress from north to south, residents and commuters are encouraged to plan ahead for periodic traffic delays.

Here is the breakdown of the official roadwork schedule, parking rules, and traffic impacts you need to know.


749286965 1359272288977422 5377038610431243270 n

Official Maple Avenue Construction Schedule

Milling operations are scheduled to start on Monday, July 20, with the final paving phases beginning the following week on Monday, July 27.

Milling Schedule (Starting July 20)

  • Day 1: Franklin Turnpike âž” Undercliff Court

  • Day 2: Undercliff Court âž” Mastin Place

  • Day 3: Mastin Place âž” Marshall Street

  • Day 4: Marshall Street âž” Spring Ave

  • Day 5: Spring Ave âž” Stillwell Place

Paving Schedule (Starting July 27)

  • Day 1: Franklin Turnpike âž” Brookmere Court

  • Day 2: Brookmere Court âž” East Ridgewood

  • Day 3: East Ridgewood âž” Stillwell Place

Note: This construction schedule is strictly weather-dependent and may be adjusted by the county if necessary.


Temporary Parking Rules and Resident Guidelines

To keep the project moving safely and efficiently, the Village of Ridgewood reminds residents living within the active work zones to follow these critical rules:

  • Clear the Work Zones: Observe all temporary “No Parking” signs. Vehicles must be moved from the designated street zones before construction crews arrive each morning.

  • Overnight & Day Parking Options: Residents who live directly inside the active work zones are permitted to park their vehicles on adjacent, non-impacted side streets during the day and overnight.

  • Follow On-Site Traffic Control: Local police officers and construction personnel will be stationed throughout the area to manage traffic control, guide pedestrians, and help maintain safety. Please stay alert and follow all posted detours.

The County of Bergen and local officials appreciate your patience, cooperation, and extra care on the road as these crucial roadway improvements are completed.

Join the new Saddle River Valley, Ramapo and Pascack Valley Communities Facebook group
https://www.facebook.com/groups/1931704860512551/
#news #follow #media #trending #viral #newsupdate
#currentaffairs #BergenCountyNews #NJBreakingNews #NJHeadlines #NJTopStories

#RidgewoodNJ #BergenCounty #TrafficAlert #RoadWork #MapleAvePaving #NJCommuters

Leave a Reply

Your email address will not be published. Required fields are marked *