Posted on

PSE&G will be Working in Ridgewood to Replace Aging Cast Iron Gas Pipes

PSEG

file photo by Boyd Loving

the staff of the Ridgewood blog

Ridgewood NJ, over the years the Ridgewood blog has reported on gas pipe line upgrades. According to the PSE&G website , PSE&G will be working in Ridgewood, May 2021 to replace aging cast iron gas pipes with new, durable plastic and/or coated steel piping – ensuring the continued safety and reliability of our gas system well into the future.

Work will take place Monday through Friday between the hours of 7 a.m. and 5 p.m., with the potential for Saturday work. The gas main replacement and services portion of the work is expected to take place through summer 2022.

When PSE&G technicians need to coordinate access to your home to connect the service line and gas meter to the new main pipeline, they will contact the homeowner to arrange a date and time to do this work. On the day of your scheduled appointment, our technicians will ask you a series of pandemic-related safety questions. During this in-home/on-property work, PSE&G technicians will be wearing personal protective equipment and will maintain physical distancing throughout the appointment. Please allow technicians access through the nearest entryway in proximity to the meter location.

If you reside on one of the streets listed, more information will be coming directly to your home.

If you have any questions, please contact our dedicated Gas Construction hotline at 1-833-661-6100 and leave a message.

Street Between Street 1 Between Street 2
Linwood Ave Paramus Border Jeffers St
Linwood Ave 155′ e/o Jeffers Ct 30′ w/o Jeffers Ct
Linwood Ave 30′ w/o Jeffers Ct John St
Linwood Ave John St 30′ w/o John St
Sollas Ct Linwood Rd End
Jeffers St Linwood Rd 10′ s/o Shelton Rd
Mary Ann Pl Jeffers St End
Pershing Ave 10′ s/o Shelton Rd Linwood Rd
Shelton Rd Pershing Ave 30′ e/o Regulator #73
Shelton Rd Regulator #73 20′ e/o Walthery Ave
Shelton Rd 20′ e/o Walthery Ave Walthery Ave
Shelton Rd Walthery Ave N Pleasant Ave
Shelton Rd N Pleasant Ave Steilen Ave
Franklin Tpke State Route 17 100′ e/o Walthery Ave
E Glen Ave 100′ e/o Walthery Ave 40′ e/o Red Birch Ct
Westfield Ave E Glen Ave Hickory St
Hickory St N Pleasant Ave End
Corona Pl E Glen Ave Concord Rd
Concord Rd Walthery Ave N Pleasant Ave
Steilen Ave Linwood Ave End
Emmett Pl Linwood Ave End
Steilen Ave Linwood Ave End
Jeffers Ct Linwood Ave End
Pershing Ave Linwood Ave 20′ n/o Wall St
Pershing Ave 20′ n/o Wall St Wall St
Wall St 60′ w/o Pershing Ave End
Wall St 60′ w/o Pershing Ave N Pleasant Ave
Fairway Rd 30′ w/o John St N Pleasant Ave
Fairway Rd 30′ w/o John St N Van Dien Ave
John St Linwood Ave Fairway Rd
John St Fairway Rd Linwood Ave
Knickerbocker Rd N Pleasant Ave 60′ w/o N Pleasant Ave
Knickerbocker Rd 60′ w/o N Pleasant Ave John St
Wyndemere Ave John St End
Pershing Ave Wyndemere Ave Eastern Ct
Eastern Ct Pershing Ave End
Pershing Ave Wyndemere Ave 70′ n/o E Ridgewood Ave
Pershing Ave 70′ n/o E Ridgewood Ave E Ridgewood Ave
Frederick St N Pleasant Ave Walthery Ave
Walthery Ave E Glen Ave Shelton Rd
Walthery Ave Shelton Rd 80′ n/o E Ridgewood Ave
Walthery Ave 80′ n/o E Ridgewood Ave E Ridgewood Ave
N Pleasant Ave E Glen Ave Shelton Rd
N Pleasant Ave Shelton Rd 80′ n/o E Ridgewood Ave
N Pleasant Ave 80′ n/o E Ridgewood Ave E Ridgewood Ave
E Ridgewood Ave Pershing Ave 10′ e/o N Pleasant Ave
Alanon Rd Lockwood Rd 230′ e/o Lockwood Rd

3 thoughts on “PSE&G will be Working in Ridgewood to Replace Aging Cast Iron Gas Pipes

  1. North Pleasant Avenue looks like Sarajevo circa 1994.

  2. And some of the streets were in great shape now they’re gonna tear it up.

    1
    1
  3. Surgical cut trench operations

    No big blow outs

    1
    2
Leave a Reply

Your email address will not be published. Required fields are marked *